| CASE
STUDY - Moor Lane Flats |
|
| Preston
City Council
|
| Project: |
Demolition
of Northumberland, Cumberland & Westmorland Houses, Moor
Lane, Preston |
| Client: |
Preston
City Council, Lancastria House, 77/79 Lancaster Road, Preston,
PR1 2RH |
| Planning
Supervisor: |
Richard
Vann Consulting Engineers, Balcombe Chambers, 21 Victoria Avenue,
Harrogate, HG1 5RD |
| Project
Manager: |
Mr.
John Bradley, Preston City Council |
| Project
Engineer: |
Richard
Vann Consulting Engineers, Balcombe Chambers, 21 Victoria Avenue,
Harrogate, HG1 5RD |
| Principal
Contractor: |
Walter
Forshaw Ltd, 7 King Street, Westhoughton, Bolton, BL5 3AY |
| WFL
Engineer: |
The
Healy Brown Partnership, Brunel House, 63 Dale Street, Milnrow,
Rochdale, OL16 3NJ |
| Contract
Description: |
The
asbestos removal, demolition and site clearance of 3 no 16-storey
residential tower blocks and remedial landscaping works on completion.
The building was of a No-Fines Concrete Frame – Explosive
Demolition. |
| Value: |
£1,400,000 |
Timescale: |
August
2000 to March 2001 |
|
|
|
|
|
Building
Construction:
The
three structures were condemned as dangerous due to spalling brickwork. They
were evacuated in 48 hours and demolished via controlled explosion within 4 months
of being declared as dangerous.
Adding to the difficulties on site was a railway tunnel that ran underneath the
middle of the site between two of the tower blocks and a listed windmill (the
only one in Preston), situated less than 10m away from the third tower block.
Demolition
Method:
The flats were soft-stripped of fixtures and fittings and the asbestos containing
materials removed prior to the pre-weakening of the structure. The structures
were then demolished using controlled explosives and the super-structure crushed
on site. The slab and foundations were broken out to a depth of 4m and the materials
crushed on site. The resultant void was back-filled with crushed material and
the site levelled.
Despite the difficulties of the contract, on blow down day, the tower blocks
collapsed exactly as planned and the project was completed on time with no problems.
Reference
Details:
Please contact WFL for reference contact details. |
|
|