CASE STUDY - Moor Lane Flats
Preston City Council
Project: Demolition of Northumberland, Cumberland & Westmorland Houses, Moor Lane, Preston
Client: Preston City Council, Lancastria House, 77/79 Lancaster Road, Preston, PR1 2RH
Planning Supervisor: Richard Vann Consulting Engineers, Balcombe Chambers, 21 Victoria Avenue, Harrogate, HG1 5RD
Project Manager: Mr. John Bradley, Preston City Council
Project Engineer: Richard Vann Consulting Engineers, Balcombe Chambers, 21 Victoria Avenue, Harrogate, HG1 5RD
Principal Contractor: Walter Forshaw Ltd, 7 King Street, Westhoughton, Bolton, BL5 3AY
WFL Engineer: The Healy Brown Partnership, Brunel House, 63 Dale Street, Milnrow, Rochdale, OL16 3NJ
Contract Description: The asbestos removal, demolition and site clearance of 3 no 16-storey residential tower blocks and remedial landscaping works on completion. The building was of a No-Fines Concrete Frame – Explosive Demolition.
Value: £1,400,000 Timescale: August 2000 to March 2001
01-Moor-Lane-Flats
Letter-Moor-Lane-Flats
Building Construction:

The three structures were condemned as dangerous due to spalling brickwork. They were evacuated in 48 hours and demolished via controlled explosion within 4 months of being declared as dangerous.

Adding to the difficulties on site was a railway tunnel that ran underneath the middle of the site between two of the tower blocks and a listed windmill (the only one in Preston), situated less than 10m away from the third tower block.


Demolition Method:


The flats were soft-stripped of fixtures and fittings and the asbestos containing materials removed prior to the pre-weakening of the structure. The structures were then demolished using controlled explosives and the super-structure crushed on site. The slab and foundations were broken out to a depth of 4m and the materials crushed on site. The resultant void was back-filled with crushed material and the site levelled.

Despite the difficulties of the contract, on blow down day, the tower blocks collapsed exactly as planned and the project was completed on time with no problems.