logo
logo header








 
7 King Street, Bolton, BL5 3AY
CASE STUDY - Plum Tree Court, Salford
City of Salford Council
Project: Plum Tree Court, Salford
Client: City of Salford Council, Building Control Department, Emerson House, Albert Street, Eccles, Salford, M30 0TE
Planning Supervisor: City of Salford Development Services
Project Manager: Mr. John Calvey, City of Salford Council Building Control
Project Engineer: City of Salford Engineering Services
Principal Contractor: Walter Forshaw Ltd, 7 King Street, Westhoughton, Bolton, BL5 3AY
WFL Engineer: Healey Brown Partnership, Brunel House, 63 Dale Street, Milnrow, Rochdale, OL16 3NJ
Contract Description: The demolition and site clearance of a 17-storey residential tower block and remedial landscaping works on completion. The building was of a Fran Concrete Panel Construction with additional strengthening at the gables.
Value: £575,000 Timescale: October 2005 to October 2006
Building Dimensions: 48m high – 500m2 on plan
Plum Tree Court
Plum Tree Court
Plum Tree Court
Plum Tree Court
Plum Tree Court
Demolition Method:

Demolition of a 17-storey residential tower block adjacent to low-rise residential properties. Scaffolding to all floors with full monarflex sheeting. Top floors deconstructed using mini-diggers and bobcats with debris lowered in skips. Through-propping to upper floors was installed for additional loads applied by the mini-excavators and debris. A crawler tower crane was utilised for lifting the floor panels and skips and lowering them to the ground. Lower floors were demolished using Hitachi EX800 Super Reach demolition excavator fitted with a concrete pulverisor with 360o rotation. Once demolished, the extensive foundations were excavated the site was finished with top soil and a knee rail boundary.
We have also completed the demolition of several other tower blocks in Salford for the same client in recent years, namely, Hanover Court, Ruthin Court, Birley Court, Lilac Court, Walter Greenwood Court
.